Georgia Mechanics Lien — Deadlines, Laws, and Filing Guide
✓ Verified against Georgia statutes · Reviewed August 2026 · By Michael Evan — Founder · 50 states · 799 rules
Georgia mechanics lien deadlines at a glance
Preliminary Notice
30 days after NOC — Notice to Contractor
Mechanics Lien
90 days — From last date of furnishing
Enforcement
1 year — From filing
Manage your Georgia deadlines and projects — start free → · All Georgia deadlines & forms
What Is the Deadline to File a Mechanics Lien in Georgia?
In Georgia, the deadline to file a mechanics lien is 90 days from the last date of furnishing labor or materials. This 90-day deadline applies to contractors, subcontractors, and material suppliers. Missing this deadline permanently eliminates lien rights.
What Is the Georgia Notice of Commencement?
Georgia property owners are required to file a Notice of Commencement before construction begins on most projects. The Notice of Commencement must be filed with the county clerk and posted at the job site. Subcontractors and suppliers who furnish after the Notice of Commencement must send a Notice to Contractor to preserve lien rights.
What Is the Notice to Contractor in Georgia?
Georgia subcontractors and suppliers who do not have a direct contract with the owner must send a Notice to Contractor within 30 days of first furnishing labor or materials on projects where a Notice of Commencement has been filed. Failure to send a timely Notice to Contractor can eliminate lien rights.
Where Do You File a Mechanics Lien in Georgia?
In Georgia, mechanics liens are filed with the Clerk of Superior Court in the county where the project property is located. Georgia uses a Superior Court filing system rather than a County Recorder system.
Frequently Asked Questions
What is the deadline to file a mechanics lien in Georgia?
In Georgia, the deadline is 90 days from the last date of furnishing labor or materials on the project.
What is a Notice to Contractor in Georgia?
A Notice to Contractor is a preliminary notice that Georgia subcontractors and suppliers must send within 30 days of first furnishing when a Notice of Commencement has been filed on the project.
Where do I file a mechanics lien in Georgia?
File with the Clerk of Superior Court in the county where the project is located.