Tennessee Mechanics Lien Statutes: Deadlines, Venues & Citations

Tennessee mechanics lien law runs on 11 tracked statutory deadlines across 9 citations. Preliminary notice is due notice-of-nonpayment — sub: 90-day rolling notice — and missing it forfeits the claim before the job ends. Liens are filed with the County Register of Deeds within 90 days of completion. This page lists every Tennessee deadline, venue, and citation tracked by the Mechanics Lien Management State System.

Where Tennessee liens are filed and enforced

A Tennessee mechanics lien is filed with the County Register of Deeds in the county where the project sits — 90 days from completion. Filing in the wrong county does not perfect the claim, which matters on projects that straddle county lines. Those are two different clocks against two different offices, and Tennessee claimants lose rights far more often by missing the second one than the first.

Tennessee deadlines by claimant role

For subcontractors and suppliers: Notice to Owner — 90 days from last furnishing (Tenn. Code Ann. § 66-11-145); Record the lien — 90 days from last furnishing (Tenn. Code Ann. § 66-11-112); file suit — 90 days from lien recorded (Tenn. Code Ann. § 66-11-126); bond notice — 90 days from last furnishing (Tenn. Code Ann. § 66-11-211); file suit — 1 years from last furnishing (Tenn. Code Ann. § 66-11-215); miller act notice — 90 days from last furnishing (40 U.S.C. § 3133(b)(2)). For general contractors: Record the lien — 90 days from last furnishing (Tenn. Code Ann. § 66-11-112). Every window runs from the claimant's own dates, not the unpaid invoice date.

Rules specific to Tennessee

Sub/supplier on RESIDENTIAL projects must serve 'Notice of Nonpayment' on owner before or within 90 days of LAST furnishing. FIX: trigger_event corrected from first_furnishing to last_furnishing per statute. Residential owner gets notice to protect themselves from double payment. Prime must file notice of lien within 90 days of last furnishing of labor or materials. File notice of lien within 90 days of last furnishing. CRITICAL: File suit to enforce lien within 90 days of recording — one of the shortest windows in the US. Do not delay. Written notice within 90 days of last furnishing on public works projects. No mechanic's lien on public property. File suit on payment bond within 1 year of last furnishing. Second-tier claimants only. No notice = no bond claim. File no sooner than 90 days AND no later than 1 year.

How Tennessee notices must be served

Tennessee requires notice-of-nonpayment — Sub: 90-day rolling notice. Accepted delivery for the notices tracked here: Certified Mail, Return Receipt Requested. Service runs to the Owner. Keep the proof of service in the project file — Tennessee disputes over whether a notice was properly served are decided on that documentation.

Public projects in Tennessee

No lien attaches to public property in Tennessee. On public state local and public federal work the remedy is a payment bond claim instead — bond notice within 90 days of last furnishing, served on the Prime Contractor and Surety (Tenn. Code Ann. § 66-11-211). 5 public-project deadlines are tracked for Tennessee.

Tennessee statute citations

The Tennessee deadlines above come from Tenn. Code Ann. § 66-11-145, Tenn. Code Ann. § 66-11-112, Tenn. Code Ann. § 66-11-126, Tenn. Code Ann. § 66-11-211, Tenn. Code Ann. § 66-11-215, 40 U.S.C. § 3133(b)(2), 40 U.S.C. § 3133(b)(1), Tenn. Code Ann. § 66-34-204, Tenn. Code Ann. § 66-34-104. Statutes are amended periodically — verify current text before relying on any date, and consult a licensed Tennessee construction attorney on a specific project.

Frequently Asked Questions

How long do you have to file a mechanics lien in Tennessee?

90 days — From completion. The filing goes to the County Register of Deeds in the project's county. See Tenn. Code Ann. § 66-11-112. The clock runs from the claimant's own last furnishing or completion, not the invoice date.

Where do you file a mechanics lien in Tennessee?

With the County Register of Deeds in the county where the property is located. Recording in the wrong county does not perfect the lien.

Does Tennessee require a preliminary notice?

Yes — Notice-of-nonpayment. Sub: 90-day rolling notice. Accepted service includes Certified Mail, Return Receipt Requested.

How long do you have to enforce a Tennessee mechanics lien?

1 year — From filing. A recorded lien left unenforced past that window generally expires and can expose the claimant to slander-of-title risk if it stays on record.

When must retainage be released in Tennessee?

Retainage released within 90 days after substantial completion. Maximum 10% retainage; reduces to 5% at 50% completion. Interest accrues on late retainage. (Tenn. Code Ann. § 66-34-104).