How to File a Mechanics Lien in West Virginia

To file a mechanics lien in West Virginia, you must record your lien with the county where the property sits within 100 days (measured from last date of furnishing). West Virginia does not require a preliminary notice before you file, so the filing deadline is the controlling date. Miss the deadline and your lien rights are gone — West Virginia courts do not grant extensions.

Step 1 — Confirm you have lien rights in West Virginia

West Virginia's recorded rules cover general contractors, subcontractors and suppliers (W. Va. Code § 38-2-8). Each of those roles has its own filing window — see Step 3. West Virginia rule detail: File mechanic's lien within 100 days of last furnishing of labor or materials. No preliminary notice required.

Step 2 — West Virginia requires no preliminary notice

West Virginia does not condition lien rights on an early notice. That removes the most common way claims are lost, but it also means the Step 3 filing date is your only checkpoint. West Virginia rule detail: File mechanic's lien within 100 days of last furnishing.

Step 3 — Your West Virginia filing deadline

West Virginia sets the window by claimant role: • General contractors: within 100 days of your last day of work or materials. • Subcontractors and suppliers: within 100 days of your last day of work or materials. The clock runs from last date of furnishing — not your invoice date. Punch-list and warranty callbacks generally do not restart it. West Virginia rule detail: File suit to enforce lien within 6 months of recording.

Step 4 — Prepare and record the lien in West Virginia

Record in the county where the property sits, under W. Va. Code § 5-22-1. The document must identify the property, the owner of record, the amount actually owed, and what you furnished. Overstating the amount can void the claim outright. West Virginia rule detail: Written notice within 90 days of last furnishing on public works projects. No mechanic's lien on public property.

Step 5 — Serve the recorded West Virginia lien

West Virginia requires service on County Clerk and Prime Contractor and Surety and Prime Contractor. Use Certified Mail, Return Receipt Requested and keep the receipt. In many states an unserved lien is unenforceable even though it appears on title. West Virginia rule detail: File suit on payment bond within 1 year of last furnishing.

Step 6 — Enforce before the West Virginia deadline expires

You must sue to foreclose within 6 months (filing) (40 U.S.C. § 3133(b)(2)). Miss it and the lien expires and title clears, leaving only a contract claim. West Virginia rule detail: Second-tier claimants only. No notice = no bond claim.

Retainage rules that affect your West Virginia claim

West Virginia treats retainage on its own schedule (W. Va. Code § 5-22A-5), so money still held back may have a different due date than your progress billings. West Virginia rule detail: File no sooner than 90 days AND no later than 1 year.

Other West Virginia requirements that void liens

• Prime must pay sub within 10 days of receiving payment from public owner. Interest accrues on late public payments. • Retainage released within 60 days of substantial completion. 10% maximum retainage on public contracts. • Public prompt payment: prime must pay sub within 10 days of receiving payment from public owner. Interest accrues on late public payments.

Frequently Asked Questions

How long do I have to file a mechanics lien in West Virginia?

West Virginia requires the lien to be recorded within 100 days, measured from last date of furnishing. The exact window depends on your role — general contractors: within 100 days of your last day of work or materials.

Do I need to send a preliminary notice before filing in West Virginia?

No. West Virginia does not require a preliminary notice as a precondition to filing, which is unusual. Your filing deadline is therefore the only checkpoint protecting your lien rights.

Where do I file a mechanics lien in West Virginia?

File with the county recorder's office in the county where the property is located. Filing in the wrong county does not preserve your deadline, and re-filing in the correct county after the deadline will not save the claim.

What happens if I miss the West Virginia filing deadline?

Your lien rights are extinguished. West Virginia courts do not grant extensions for missed mechanics lien deadlines. You would be left with a breach-of-contract claim against whoever hired you, which carries no security interest in the property and is far harder to collect.

How long does a mechanics lien last in West Virginia?

Once recorded, you must file suit to enforce within 6 months (filing). If you do not, the lien expires automatically and no longer clouds the property's title.