Delaware mechanics lien deadlines at a glance

Preliminary Notice

None — N/A

Mechanics Lien

120 days — From last date of furnishing

Enforcement

1 year — From filing

Manage your Delaware deadlines and projects — your first project is on us → · All Delaware deadlines & forms

Delaware Payment Bond Claim — official construction notices posted on a jobsite permit board (Mechanics Lien Management Payment Bond Claim guide, 2026)
A Delaware payment bond claim under 29 Del. C. § 6962(d)(9) is a suit on the 100% bond required on large public works contracts. The statute requires no claimant notice . An unpaid sub or supplier sues in the agency’s name within one year after the prime contractor ceased work if the bond says so, and otherwise within three years after the last work on the contract.

Why Delaware Public Work Runs on a Bond

On private work, an unpaid Delaware sub or supplier files a statement of claim in Superior Court within 120 days from completing its labor or its last delivery, under 25 Del. C. § 2711(b). The Delaware mechanics lien guide walks through that process. A Red Clay or Christina school building, a DelDOT bridge on Route 1, a state service center in Dover or a Sussex County wastewater plant is different. A lien does not attach to public property, so the protection is the bond the prime posted when it signed the contract. Delaware does not have a stand-alone Little Miller Act chapter. Its bond rule sits inside the state procurement code, in 29 Del. C. § 6962(d)(9) for large public works contracts, with a parallel rule in § 6927 for other bonded state contracts. What makes it unusual is what it leaves out. There is no 90-day notice , no notice to the surety and no filing with the agency. A claimant simply sues on the bond, and the time limit depends partly on what the bond form says. The Mechanics Lien Management Method treats a Delaware public job as a one-calendar file . There is no notice clock to protect, so the single date that matters is the suit date. Get the bond, read its limitation clause, and calendar the earliest date that could apply.

The Bond: 100% of the Contract on Large Public Works

Section 6962 applies to any state contract with an agency as a party whose probable cost is greater than the small-public-works amount set by the Contracting and Purchasing Advisory Council under § 6913. The statute itself does not print a dollar figure, so check the current threshold with the agency or the Office of Management and Budget. When the formal contract is executed, the successful bidder also executes a bond to the contracting agency, with a corporate surety authorized to do business in Delaware, in a sum equal to 100% of the contract price , on the standard form issued by the Office of Management and Budget (§ 6962(d)(9)a.). The bond is conditioned on faithful performance of the contract, including payment in full to every firm furnishing material or performing labor of all sums due it (§ 6962(d)(9)b.). Delaware uses a single performance bond that carries the payment condition, rather than a separate payment bond as in many states. For a claimant, the result is similar. The surety stands behind the prime’s duty to pay you, and the bond is the full contract amount.

No Notice Required — and Why You Should Send One Anyway

Section 6962(d)(9)d. gives a right of action to every firm furnishing material or performing labor under the contract for which the successful bidder is liable. It does not condition that right on any notice. First-tier subs, lower-tier subs and suppliers stand on the same footing, subject only to the requirement that the prime be liable for the sum claimed. That is a real advantage over states such as Pennsylvania and Maryland, where a missed 90-day notice ends a remote claimant’s bond rights. But silence in the statute is not a strategy. A short written demand to the prime and the surety, with your invoices and the amount due, does three useful things: If the bond or subcontract does impose a notice term, follow it to the letter. Ask a Delaware construction attorney whether that term can bar a claim the statute allows.

The Suit Clock: One Year or Three, Depending on the Bond

The claimant sues for its own use in the name of the agency , in any court of competent jurisdiction, for the sums due it from the successful bidder. The time limit has two branches in § 6962(d)(9)d.: Both branches count from the prime contract , not your subcontract. If you are a sitework sub who finished early, your clock may be longer than you think. If you are a finish trade and the prime walked off before you were done, it may be shorter. Keep a record of when the prime demobilized, when the last punch-list work happened, and when the agency accepted the project. Section 6927 uses the same rule for other bonded state contracts, with the suit in the name of the State or the contracting county. Delaware’s private prompt-payment fee statute, 6 Del. C. § 3509, expressly excludes public works contracts awarded under chapter 69, so do not assume a statutory fee award. Look for a fee clause in the subcontract instead.

Every Delaware Public-Project Deadline in One Table

The Mechanics Lien Management State System calendars the conservative one-year suit date from the prime’s completion date you enter, so you are never relying on the three-year branch by accident. Private-work rules are on the Delaware lien statutes page, and the calculator is on the Delaware mechanics lien hub . The last row matters for any supplier serving Dover Air Force Base or other federal facilities in the state. The federal Miller Act requires a 90-day notice from second-tier claimants and runs suit from the claimant’s own last furnishing, the opposite of Delaware’s state rule on both counts. See the mechanics lien vs. bond claim comparison.

Get the Bond, Read the Clause, File on Time

Delaware Public Works Workflow Request the bond from the agency at award and read its limitation clause. Send a written demand to the prime and surety when payment stalls. Track the date the prime ceased work. Sue in the agency’s name within one year of that date unless you have confirmed the bond has no limitation clause. Pair it with these resources: Because the claim is a lawsuit against the surety from the start, connect early with a Delaware construction attorney through the Mechanics Lien Management network, or request a formal attorney review of the claim file.

In Delaware, the Lawsuit Is the Deadline

The Mechanics Lien Management deadline calculator tracks the bond suit date on every Delaware public job. Miss the deadline and you lose your claim rights entirely.

Frequently Asked Questions

Does Delaware require a notice before a payment bond claim?

Not by statute. 29 Del. C. § 6962(d)(9) lets every firm furnishing material or performing labor under a large public works contract, for which the contractor is liable, maintain an action on the bond. Unlike the federal Miller Act and most state versions, it sets no 90-day notice and no other claimant notice as a condition of suit. Read the bond form anyway, and put the contractor and surety on written notice of the unpaid balance as a practical matter.

What is the deadline to sue on a Delaware public works payment bond?

It depends on the bond. Under 29 Del. C. § 6962(d)(9)d., if the bond so provides, no suit may be commenced after one year following the date on which the contractor ceased work on the contract. Otherwise, suit may be commenced at any time within three years following the date the last work was done on the contract. Assume the one-year limit applies until you have read the bond and confirmed it does not.

Whose last day starts the Delaware bond suit clock?

The prime contractor's, not yours. The one-year limit runs from the date the successful bidder ceased work on the contract, and the three-year limit runs from the date the last work was done on the contract. A sitework sub that finished in March may still have time if the prime worked into the fall. A finish trade that worked to the end has less margin than it thinks if the prime walked off early.

How big is the payment bond on a Delaware public project?

On a large public works contract, 100% of the contract price. Section 6962(d)(9) requires the successful bidder to execute a bond to the contracting agency, with a corporate surety authorized in Delaware, on the standard form issued by the Office of Management and Budget. The bond is conditioned on performance of the contract, including payment in full to every firm furnishing material or performing labor of all sums due it.

In whose name is a Delaware bond suit filed?

On a large public works contract, the claimant sues for its own use in the name of the contracting agency, in any court of competent jurisdiction (29 Del. C. § 6962(d)(9)d.). On other bonded state contracts governed by 29 Del. C. § 6927, the suit is brought in the name of the State or the contracting county. The same one-year-or-three-year limit applies under both sections.

Can I file a Delaware mechanics lien on a school or DelDOT project?

No. The 25 Del. C. chapter 27 statement of claim is a private-property remedy, and a lien does not attach to public property. On a Christina School District building, a DelDOT bridge, a University of Delaware or state agency project, or a county facility in New Castle, Kent or Sussex, the security is the contractor's bond. Federal work at Dover Air Force Base runs under the federal Miller Act instead.

How does the Delaware bond deadline compare with the private lien deadline?

On private work, a subcontractor or supplier files a statement of claim within 120 days from completion of its labor or last delivery of materials under 25 Del. C. § 2711(b), and a prime contractor within 180 days after completion of the structure under § 2711(a). On public work there is no notice to miss, but the suit itself is the deadline, so the bond claim calendar is about filing a lawsuit, not recording a document.